Project Management Processes - Under development
A procedure is an established method of meeting a business requirement
or a traditional order of processes followed to meet a particular outcome.
A process is defined as a series of events or steps taken to achieve
completion of a procedure.
In Quality Assurance, you start with a companies core procedures, then
detail the processes required to achieve and monitor your effectiveness
of meeting these Procedures, and as appropriate, provide detailed work
instructions on how to complete each process.
The same analogy holds true for a project. A project is like a procedure
and requires processes to be carried out at each stage of the project
to archive and monitor the effectiveness of completing the project on
time and within budget. Within Prince 2 there are eight key processes,
each one is applied to the project as appropriate:
- Directing a Project (DP) - this is a project board/Program
management process that runs from the start of a project through to
its completion, and includes the following steps:
- Planning (PL) - Interactive steps involved in planning and
re-planning the delivery of required products or steps within a project
and it's associated stages. This includes:
- Writing a description of the final product
- Defining a breakdown of the product components
- Define the product quality requirements
- Creating a flow (Gantt) chart showing the creation of the product
components and their interdependencies
- Identify the activities required to create the product and its
components
- Estimate the duration and effort required for each activity
- Asses all risks
- Calculate the costs
- Identify the management control points
- Document the plan, all assumptions, and justification
- Starting a Project (SU) - to if you you have a viable and worthwhile
project, the following process steps are completed:
- Ensure that you are authorised to undertake the project
- Confirm that the information is available to meet the project
objectives, scope, and manage any constraints.
- Design and appoint the project management team
- Agree the steps to be taken to deliver the project
- Create, agree, and initiate the Stage Plan
- Initiating a Project (IP) - the first stage of a project, which
provides a firm foundation by scoping the management of the project.
This process includes:
- Checking that everyone understands the scope and objectives of the
project
- Confirming that an approved business case exists
- Checking that the project is adequately planned and costed
- Carry out a review of any identified risks
- Obtain commitment from the project board to proceed to the next
stage
- Managing Product delivery (MP) - Delivery of product and components
by the project team
- Project team agree and accept work packages from the project manager
- Ensuring completion of the required works
- Reporting on progress
- Ensuring quality requirements are met
- obtaining approval for completed products & components
- Controlling a Stage (CS) - the day to day management of project
activities. As appropriate, each stage includes the following steps:
- Approving work carried out by the project team
- Monitoring and reporting on project progress
- Capturing and logging project issues
- reviewing and evaluating required changes
- Carrying out any corrective actions
- Confirm delivery of completed steps from the project team
- Managing Stage Boundaries (SB) - The project managers responsibilities
at the end of each stage, or enable corrective action following an exception,.
As appropriate this includes:
- Reporting on the delivery of the stage products and components
- Recommending any follow up actions
- Planning post project review (s)
- Reviewing project management and reporting any lessons learned
- Project decommissioning and handover
- Closing a Project (CP) - Ensure a clear end and handover of
a project following either successful completion or or early termination
of the project. This includes:
- Report on the completion of project objectives defined in the
Project Initiation Document
- Recommend any required actions
- Plan post project review
- Assess how the project was managed and report any lessons learned
- Decommission the project and as appropriate handover the product
Project components

There are a number of key components are used in the Prince 2 methodology,
moving clockwise starting with the Business Case:
Business Case
A Business Case contains the details, reasons, and
justification for carrying out a project. It includes a cost benefit
analysis of all the components affected by the project, no matter how
small. This should include any impact on core procedures, related processes,
personnel, accommodation, or products
Organisation
The organisation must include, and have agreement (authorisation) from
the owners of:
-
Requirements
Definition (i.e. Customer SOR etc...)
- Budget Holders
- Resources
- Change Management
- Day to Day Task Management
- Standards requirement
In some instances, for example, with small projects, the same person
may own more than one of these elements. A typical project organistion
would include the following people:
Project Board - represents the interest of the customer, user,
and supplier. It provides direction and management during the life
of the project. Ensuring the project remains on track, as defined
in the Business Case, and within budget whilst retaining quality.
Responsibilties include:
Project Startup
- Approve project brief and authorise startup
- Agrees project tolerances
- Defines project assurance criteria
- Agree the project managers objectives and responsibilities
- Commits resources to initiation stage
- Authorise the Project Initiation Document
Project Stages
- Review the project status and the end of each stage
- Authorise the start of the next stage or project termination
- Confirm that project is on track in line with the Business Case
- Review and authorise exception plans
- Approve any project changes
- Provide ongoing guidance to the Project Manager
- Report progress to corporate management
Project End
- Confirm successful delivery of the project Business Case
- Confirm agreement for handover of project outcome to operations/support
- Approve End of Project Report
- Review lessons learned
- approve the Post Project Review Plan.
- Authorise Project Closure
Project Board Executive - As owner of the Business Case, the
executive has ultimate responsibility for the success of the project,
and ensures that the solution is fit for purpose, stays within budget,
whilst balancing the needs of the business, users, and suppliers.
Project Board Senior User - responsible for the accurate specification
of the requirements, making sure that delivery is fit for purpose and
within the constraints of the Business Case.
Project Board Senior Supplier - repsonsible for the design,
development, procurement, and implementation of the project products.
Project Manager - Runs the project on a day to day bases on
behalf of the project board. Repsonsible for ensuring that the project
delivers quality product on time and within budget. The project manager
will:
- Project documentation - Project Initiation Document, Project and stage
plans
- Obtain Project Plan approval from the Project Board
- Define and allocate responsibilities for work
- Monitor and control the progress of the project according to the Business
Case.
- Manage risk and contingency plans
- Agree performance and delivery of work with Team Managers
- Schedule stage control points
- Manage Project Assurance
- Prepare and p[resent project reports to the board
- Maintain risk, quality, and issue logs
- Mange excpetion plans
Team Manager - As required, manages direct and third party work
suppliers:
- Negotioates work requirements with the Project Manager
- Plans and allocates work within the teams
- Monitor progreaa and initiate any corrective actions
- Report progress to the Project Manager
- Liaise with Project Assirance and maintain records of quality checks
Project Assurance - Independant to the Project Manager, Project
Assurance monitors the project to assure that the project specification
and standards relating to the Business Case continue to be met. This
should ensure;
Business
- Project costs and schedule are being monitored
- Project remains vaiable and provides value for money
- Project meets strategy and programme requirments
- Focus is maintained within the Business Case
- Communication between all parties is maintained
- Risks are being contraolled
User
- An acceptable solution is developed and maintained
- Needs and expectations are being managed effectively
Specialist
- Communication is maintained between customer and suppliers
- The needs of the specialist work are identified and recognised
- the scope of the project remains within scope
- Required standards are being used and are effective
Project Support - Provides support to one or more project as
required, and covers:
- Administration of project documentation including control reviews,
meetsings and communications.
- Provides expert assistance to the project for project tools, estimates,
planning and standards.
Plans
Plans
should be hierarchical, for example, they should include the following
levels:
Programme - These are optional plans used when
managing a number of projects that may use common (shared) resources.
Project - A high level plan showing key deliverables (stages)
and major control (review) points of the project. It is used to summarise
and monitor costs against a baseline as you progress through a project.
Stage - A stage Plan contains the day to day detail details required
to manage one stage of a project. Stages may be sequential, or in some
cases concurrent, to other project stages.
Team - These are optional plans used to manage more detailed
activities within a stage, and would be developed alongside the development
of the associated stage plans.
Exception - These plans are common to other plans and are used
at any time during a project when the project manager identified an
exception that deviates beyond tolerance levels set by the project board.
An exception plan replaces an existing plan showing the work and resources
required to react to an exception or deviation
Plans are often represented as a flow (Gantt) chart:

All plans should include the following details at the appropriate level:
- Description of the plan
- Pre requisites and assumptions
- External Dependencies
- Tolerances
- Risk Analysis
- Resources and Budget requirements
- Graphical Summary, for example, a Gantt Chart
Controls
A Schedule of Controls is required for each stage of
a project, which is reviewed on a regular basis with appropriate reports
generated and logs kept . As well as monitoring and reporting on the
quality and progress of a project against the schedule, controls aid
any decision that may be required regarding the continued viability
of a project against the business case.
Controls include the following decissions:
Project Initiation - Yes or No?
Stage end assessment - On courSe? risks managed? Still Viable?
Move to next stage?
Highlight Reports -
Exception Reports -
Project Closure -
Stages -
Tolerances -
Product Descriptions -
Work Packages -
Project Issues -
Risk Log -
Risk Management
Pending
Project Quality
Pending
Config' Management
Pending
Change Control
Pending
|